The competition authority will assess how the creation of the merged entity will affect the balance of power in the renewable energy sector and whether the transaction will distort normal competition.
The project relates to the ‘Summa FIBA Enerji’ consortium’s victory in the second round of tenders for the development of renewable energy organised by the Ministry of Energy (the results of which were approved by the government in November 2026).
The following parameters are planned as part of the deal and the project:
- Installed capacity: the total capacity of the onshore wind farm will be 52 MW, of which 40.5 MW will qualify for the status of a large authorised producer (guaranteed state support).
- Tariff and support period: the fixed electricity sale price resulting from the tender is 1.2528 lei/kWh (excluding VAT) for a period of 15 years. The company will sell electricity from the remaining 11.5 MW on the open market at market prices.
- Battery Energy Storage System (BESS): a mandatory condition of the tender is the installation of industrial energy storage batteries with a capacity of 10.125 MWh (calculated at 0.25 MWh for each megawatt of installed capacity).
- Timeline: no more than 36 months are allocated for the construction and commissioning of the wind farm and energy storage systems from the date of publication of the relevant government decree in the Monitorul Oficial.
The competition authority is assessing whether the establishment of the joint venture is consistent with a normal competitive environment, in accordance with the Competition Act and the Regulation on Economic Concentrations. The authority invites interested economic operators to submit their comments and views on the potential impact of the transaction on the market.
Follow our updates
Have information for the newsroom? Share it with Logos-Press





























Comments
0No comments yet. You can start the conversation.
Comments are open to readers with a Logos Press account.
Sign in to comment