He recalled that the line was ready in the middle of this year. Voltage tests had even been carried out. Then, at the start of summer, a problem arose with a transformer, which was sent to Spain for repair. On 23 or 24 September, it returned, and it was installed and connected.
“The latest deadlines the company has given us are late October to early November for the project to commence commercial operation,” said Junghietu.
The Vulcănești–Chișinău line, also known as the ‘Energy Independence Line’, was due to come into operation last December. Since then, its commissioning has been postponed for the sixth time.
This story was translated with the assistance of artificial intelligence.The translation was also reviewed by the Logos Press editorial team.