This was announced by the company’s president, Konstantin Efimenko, according to Interfax-Ukraine.
“We have already completed construction of the building, and by September 1, we will finish installing all the utility lines. We have already ordered the bottling line. By the end of June, we will sign contracts for the reactor equipment and all other process equipment. We will begin operations in December 2027,” Efimenko said.